
Club newsNew Year update from the Anfield Road Stand expansion
Foundation work is now complete and these new behind-the-scenes pictures feature concrete core wall panels and the first concrete stairs, which will provide the stability for the building.
The first two concrete wall panels are in place on the eastern core, along with the first flight of pre-cast concrete steps. The remaining core starter bars are also in place to frame the central core of the building.
Work on the stand expansion – which will add around 7,000 seats to the stadium’s overall capacity – began last September and is anticipated to be ready for the 2023-24 season.
Check on the progress on-site in the gallery below.
Latest news
Match reportLiverpool beat Everton to reach Abode Women's FA Cup quarter-finals
VideoNottingham Forest 0-1 Liverpool: Watch free highlights
ReactionArne Slot press conference: Liverpool's late win at Forest, mentality, Mac Allister and more
NewsLiverpool's Carlsberg Player of the Match v Nottm Forest revealed
ReactionAlexis Mac Allister: It's a really good day - but we must improve